February, 2002
The idea of building a hotel
in Pereslavl had emerged at
the Modular Buildings Plant long
before the construction started.
|
|
|
|
Mid-19th century
Trading rows and inns were
traditionally located on what
is known today as
Plescheevskaya Street.
|
|
|
 |
|
 |
March, 2002
With the support of the
mayor of Pereslavl a
place for the future hotel
has been selected.
|
|
|
|
April-May, 2002
The land for the hotel is
"a- waiting" while the
necessary permits and
approvals are being received.
|
|
|
 |
|
 |
June 10 – July 10, 2002
A snapshot of the assembly
process: construction of the
foundation frame and the
mounting of the walls.
|
|
|
|
June 10 – July 10, 2002
Module walls are filled with
thermal and sound insulation.
The roof is built on hinges to be
quickly set up on site.
|
|
|
 |
|
 |
May 25–June 10, 2002
Construction of the hotel
foundation.
|
|
|
|
July 3 – 12, 2002
Transporting the first module
to the construction site. The
process of the building setup
is underway.
|
|
|
 |
|
 |
July 3-10, 2002
16 hotel modules have
travelled along the same route
from the plant to
the construction site.
|
|
|
|
July 3, 2002
Setting up the first module
on the foundation.
|
|
|
 |
|
 |
July 3-10, 2002
The hotel modules were
set up and assembled,
one by one, within less
than a week.
|
|
|
|
July 10, 2002
The roof was lifted and
set up – it is an assembly
process, not one of
construction.
|
|
|
 |
|
 |
July 17, 2002
Work on exterior finishing
is progressing at a fast pace.
|
|
|
|
July 22, 2002
After all the utility services had been
connected, the dug up patch of land
to the right of the building was
properly landscaped and asphalted.
|
|
|
 |
|
 |
July 22-25, 2002
The building acquires a look
of completion. The fence setup
is finished. |
|
|
|
July 27, 2002
The Hotel Zapadnaya, now settled
unseparably on the right bank of
the beautiful Trubezh River, is
awaiting its first guests.
|
|
|